Basement Floor:Ground Floor:First Floor
-Hypermarket-90 Shops
-65 Shops-Car Parking-Car Parking
-car Parking
-Total Car Parking(B+G+Four),2394 +ots
Total Plot area :209,600s.q.m.
Total Costruction Cost :AED 550 Million.
1.Water Cooled Chiller ,828 Tr-5Nos Chilled waterPumps are variable fre quency Drive for saving the energy&5nos.colling Towers,Each167 I/S capacity.
2.All the Ac units selected low static type and Fresh air Handling unit selected with Heat recovery Wheel+Horse Shoe Heat pipe for Energy saving
3.In the project all the area considered Noice level NC55-45
4.Chilled water Energy meters (Btu meters(provided all the retails
5.The total power requirement 21,000kw(21 Megawatt)
6.In project all the lightings selected LED type based on the Lux Calculation
7.Provided Uninterruptible Power Supply (UPS) for life safety ENERGY SAVING SYS TEMS
The following techniques are applied to save energy and henceless running cost for the whole building.
-Energy Saving Lamps,LED lights shall be provided wherever possible.
-Power factor cooection capacitors,VFD Chilled water pumps.